13.6 MW Biomass Plant: ECO 4–5 Replacement

REHABILITATION · POWER PLANTS / BIOMASS

Biomass plant economizer works

Turnkey replacement of ECO 4–5 packages fabricated from seamless 16Mo3 tubes (Ø42.4 × 4.0 mm, European origin), including pipe-bend manufacturing, assembly and testing, plus replacement and welding of boiler wall pipes.

Scope of work

Economizer

  • Pipe supply
  • Pipe bending and welding
  • Scaffolding installation
  • Removal of economizer module pipes
  • Installation and welding of new pipes
  • Hydrostatic test
  • Insulation

Boiler

  • Scaffolding installation
  • Dismantling of damaged pipes
  • Installation and welding of new pipes
  • Hydrostatic test

On site